Moisture Intrusion Test
1.
Visual inspection of the house
The object is to identify and note any
problem areas or details that vary from EIFS Industry Member Association
(EIMA) standards for inclusion in the report.
These items should be noted in the report, as well as referencing the
proper EIMA Standards. Inform the client that it is important that they
determine the Manufacturer of their EIFS installation. Specifications
for installation do vary slightly among the Manufacturers.
The general condition of the construction of the house and stucco (EIFS)
wall-cladding should be determined.
Terminations:
Foam should be backwrapped, have an expansion type joint where EIFS
terminates on a driveway, patio, sidewalk, etc. This is typically not
done, because the flow of residential construction does not allow for
this. The exterior concrete flatwork is usually done late in the
schedule.
Roof termination:
Should be held off of roof a minimum of two (2) inches and
backwrapped.
Below grade termination:
Foam should not terminate below grade. The foam substrate should be
backwrapped and sealed to the foundation approximately 6-8 inches
above grade. This mainly serves two purposes; it prevents wicking
action of the foam and eliminates a termite path into the structure.
The foam creates an ideal environment for the termite, which is
impossible to treat.
Backwrapping:
Where the foam substrate terminates, it should be backwrapped, in
order to provide for proper protection of the foam. Backwrapping also
provides for improved attachment of the substrate to the sheathing.
Backer Rod/Sealant: Windows -
Expansion Joints - Grade Terminations:
The usage of backer rod and sealant is necessary for the proper
construction of an isolation type of joint. Flexible and waterproof.
Expansion Joints: Dissimilar
Materials - Floor Bands:
Expansion-joints should be used where EIFS terminates, or meets a
dissimilar material. The typical expansion joint is a flexible,
watertight joint utilizing, backer rod and sealant. Expansion joints
at the floor bands are usually 3/4 inch in width; typical joint at
windows and doors is 1/2 inch,
Horizontal Surfaces: Trim
Bands Quoins:
There should be no horizontal (flat) surfaces. All surfaces should
slope away from the structure.
Flashing:
Flashing should be utilized to properly direct water away from the
structure. Doors, windows and deck attachments are the most typical
areas where flashing is used. Although flashing has been required for
several years, many builders felt that flashing on stucco-type
exteriors was not necessary. Check for proper flashing details.
Flashing points, where a gutter meets a side wall, are one of the most
common areas for excessive moisture intrusion.
Penetrations:
Penetrations should be properly sealed. No foam should be exposed.
Look for any penetration, not only the obvious. In addition to pipe
penetrations, look for fasteners, lights or any object that passes
through the EIFS wall-cladding materials.
Damaged Areas:
Damaged areas should be noted in the report. Areas that are cracked or
damaged should be repaired. The finish coat and base coat material
should be removed. If the insulation board is not damaged, the base
coat, mesh and finish coat can be reapplied. If there is damage to the
insulation board, remove and replace the damaged section of insulation
board, reapply base coat, mesh and finish coat.
2. Test Probe
The inspector should
prepare a test probe and the holes filled with a sealant labeled in
compliance with ASTM-C920, or of a type recommended by the EIFS
Manufacturer. The test probe and the color of the sealant should be
approved by the homeowner/client.
3. Moisture Detector
The house should be
scanned with a Tramex Wet Wall Detector or equivalent. The idea is to
scan, or test, every area where moisture is obvious - but also those
areas that might not be so obvious. Including, but not limited to:
Corners, outside and inside, both
faces-minimum every 2 ft.
Around doors and windows, and below.
At the band, each floor level, every
3 ft.
At flashing points - sidewall and
gutter return areas.
Around all wall penetrations.
It should be emphasized that the
scanners available at this time do not provide adequate information for
rendering a conclusive Moisture Intrusion Inspection Report. The
technology is limited to providing a basic indication of a possible
elevated level of moisture in the area indicated. The areas which the
scanner indicates an elevated level of moisture should then be probed
using a reliable moisture meter with probes of an adequate length.
The use of a scanner is not mandatory. If the individual doing the
testing wishes to probe the entire house, this is acceptable. If this is
the case, the amount of probing required is extensive.
4. Reporting
The high readings, along
with the specific location of the readings, should be noted in the
report. This is necessary so that in the future, the readings can be
referenced for a follow up test. A reference for future testing should
be indicated in the report. Time frame should be approximately 6-18
months.
The report should indicate the
following concerning the readings:
10 to 19% - Moisture is
present in the wall. Additional sealant at the specific area should be
sufficient.
20 to 29% - The source of the
water intrusion should be identified, if possible. Appropriate
corrective action should be taken to stop the entrance of the water.
In many cases, a particular detail may be corrected, or additional
sealant installed as a satisfactory corrective measure.
30%+ - This is the fiber
saturation point of wood, the level at which decay rapidly begins to
occur. The EIFS at these areas should be removed so that the framing
can be inspected for indications of rot or decay. Any damaged areas
should be repaired or replaced, as necessary.
The problem areas should be clearly
identified in the report. There should be a system for identifying the
probed areas. This is necessary so that the. house can be effectively
re-tested. Another inspector may be doing the re-testing.
Other Types of Inspections
It is possible to do a mostly visual inspection of a house and observe
conditions that do not meet current EIMA Installation Standards. This
form of Inspection, or Consulting Service, should not be confused with,
or claimed as, an EIFS Moisture Intrusion' Inspection. |